Update 1pm
Plan for the next 1-2 weeks:
1) rebuilding 20KV for SBG3
2) rebuilding 240V in SBG1/SBG4
3) verifying DWDM/routers/switchs in the network room A (SBG1). checking the fibers Paris/Frankfurt
4) rebuilding the network room B (in SBG5). checking fibers Paris/Frankfurt
Update 4pm
We plan to restart SBG1+SBG4+the network by Monday March,15 and SBG3 by Friday March,19. In RBX+GRA we have the stock of new servers, pcc, pci ready to be delivered for all the impacted customers. Of course for free. We will add 10K servers in the next 3-4 weeks.